  • Padding timesheets to the budget

Padding timesheets to the budget breaks next year's price

I think padding or trimming timesheets to match the budget breaks next year's price. The next budget is built from this year's "actual" hours, so hiding the difference leaves the firm pricing from the same wrong number. Record what happened, write off the difference openly, and change what the review asks.

A man redraws the long orange Actual bar to match the short Budget bar beside it

Why do people record the budget instead of the real hours?

Writing the real number gets you questioned; writing the budget gets you left alone. A thread in r/Accounting called "Coworkers lying on timesheets" drew 139 replies, and many of them were not shocked. They described timesheets as a science: if you come in under budget you add hours until it matches, and if you go over you eat the extra and write the budget anyway. Partners bill the budget regardless, the argument goes, so the real figure only matters to the person who has to explain it, and the advice to always record actuals came across as naive.

I understand that view. Most of the people describing it are trimming their own hours, not inflating a client's bill. They are absorbing the overrun themselves so the engagement looks the way the partner expected. On a fixed fee, the client pays the same either way. It feels like a private cost, quietly paid, with nobody harmed.

The view is also accurate about incentives. Anyone who has watched a colleague get pulled into a meeting for being over budget on a job that was underquoted learns the lesson fast. The timesheet that matches the budget is the one nobody reads.

What does a padded timesheet actually break?

The next budget. When a firm prices next year's engagement, the first thing it looks at is what this year's job actually took. If the actuals are the budget, the firm learns nothing, and the same job is priced the same way again, with the same overrun hidden in the same place.

This is the part the "everyone does it" view leaves out. It treats the timesheet as a report to the partner about whether you behaved. I think its real job is to measure the work so the firm can set prices. Treat it only as a report to the partner and changing it can seem harmless. Treat it as a measurement and the damage is clear: every decision built on it inherits the error.

It works in both directions. Padding a short job up to the budget makes that work look more expensive than it is, so the firm may overprice it next time or turn away work it could have done profitably. Trimming a long job down to the budget does the opposite: the firm keeps underpricing the work that is hardest to deliver.

What does a job that never gets repriced look like?

Picture a firm that budgets 20 hours for a client's year-end. It takes 31 every year. The staff on it write 20 against the client and absorb the rest in "admin" or in evenings nobody records. The timesheets say the budget is right, so the next year's fee is set on 20 hours again.

Three years later the partner wonders why the practice is always busy and the margin is always thin. Nothing in the records explains it. The 11 hours a year were real, 33 over three years on one client, and the timesheets hid every one of them. Multiply that by every engagement where the same quiet trimming happens, and the firm has a pricing problem it cannot see, because the only instrument that could show it was set to agree with the plan.

Price the job from the hours it took, not the hours it was supposed to take. Pricing from tracked hours only works if the tracked hours are true.

Is the timesheet the problem, or the review?

The review. People pad because the person who records the real hours is the one who gets asked why. Change what the review asks, and most of the reason to pad goes away.

A manager who opens the budget report and asks "why are you over?" has turned the timesheet into evidence against the person who filled it in. A manager who asks "what took longer than planned?" has turned the same overrun into information about the job. The first question teaches people to make their timesheets match the budget. The second gets you an answer like "the client sent the bank statements in three batches" or "the payroll reconciliation was a mess again", which is exactly what you need to price the job next year.

The second question also changes who owns the miss. An overrun on a job that was underquoted belongs to the quote, not to the junior who did the work. If the review makes that clear every time, the junior has no reason to hide it.

Is a write-off a failure?

No. Record the real time and write off the difference openly. A visible write-off is a pricing note. An invisible one is a habit.

On a fixed-fee job, the client's invoice does not have to change at all. The timesheet says 31 hours, the invoice says the agreed fee, and the gap is recorded as a write-off with a one-line reason. That record is worth more than a tidy budget report, because it tells the person setting next year's fee exactly how far off the quote was and why.

A woman marks the extra part of a real-hours bar as a write-off, with a longer bar on next year's card

Write-offs only feel like failure in firms that count them against individuals. Counted against the engagement, they are a record of the jobs the practice is underpricing, with the size of each gap already worked out.

Does it matter more when the client pays by the hour?

Yes, because then the two directions stop being equal. On an hourly engagement, padding a short job up to the budget means invoicing the client for time nobody worked. That is no longer a pricing error. It is a billing error with the client's money on the other side of it, and it is the version that ends relationships when a client asks to see the entries.

Trimming on an hourly job is a discount nobody agreed to. It may be the right call, since a client should not pay for a junior's learning curve or a firm's own mistakes. But it should be a decision someone makes on the invoice, not a number someone quietly typed on a timesheet. Keep two figures apart: the hours the work took, which are a fact, and the hours you bill, which are a choice. Padding is what happens when a firm lets the second overwrite the first.

What does recording the real hours cost?

In the short run, it can make some people look slow. If everyone else on a team writes the budget and one person writes 31 hours, that person stands out, and not in a way they chose. Some firms do use hours against staff, and in those firms the honest timesheet carries a real personal cost.

I accept that, and I do not think it is an argument for padding. It is an argument about the firm. Where hours are used against people, the problem is the review, and no timesheet fixes it. A better form, a new tool or a policy memo about accuracy will produce the same numbers if recording the truth still gets people punished.

For a firm owner, the cost is a few uncomfortable months. The first honest budget reports will look worse than the padded ones did, and some engagements that seemed fine will turn out to have been losing money for years. That is not new damage. It is the old damage becoming visible, which is the only way it ever gets fixed.

What should a time tracker do about it?

Record what happened, to the minute if needed, with no rounding the user did not choose. A tracker that quietly rounds every entry up to the next quarter-hour is doing its own small version of padding, and it does it on every entry, so the error adds up over a month without anyone deciding it should.

Rounding has its place on an invoice, where a firm and its client agree on a billing increment. It does not belong in the record of what the work took. Timen has no rounding setting at all: an entry is the time that was tracked or typed, and any minimum or increment is applied by the person invoicing, where it can be seen. Whatever tracker you use, the test is the same. Could the number on the timesheet be wrong without anyone having typed a wrong number?

A weekly time review where each overrun gets one line of explanation turns a year of entries into something you can price from.

So what should go on the timesheet?

The hours the work took. Not the budget, not the number that avoids a conversation, not a rounded figure nobody chose. If the job ran over, write it down and write off the gap with a reason. If it ran under, write that down too.

Then change the question the review asks. "What took longer than planned?" costs nothing, and it is the difference between a timesheet that protects the person filling it in and one that tells the firm what its work costs. Padding feels like a private kindness to the budget. It is really a decision to price next year's job on a number everyone knows is wrong.